April 2019 update

It’s been a busy winter of construction at the Operations Building! 

A great deal of progress has been made on the Human Resources department in the administration wing. Crews are currently working on the interior. Walls are soon to be enclosed and then they will continue with plumbing, electrical, fire protection, and controls work.

As the spring progresses, crews will begin paving the parking lots around the building.

In the operations wing, concrete work in the main bays has been completed and crews are currently finishing the flooring of the upper level. Outside, the fuel depot is soon to be installed.

Recent construction images can be viewed on the Media page.