February 2019 update

A lot of progress has been made on the Operations building over the last several months! Construction is now 65 per cent complete.

In the administration wing, crews are currently building walls and rooms, and glass enclosures. All windows are expected to be installed by the end of February. Crews will then proceed with dry walling, and indoor electrical and mechanical work, followed by paint and doors.

Siding has been completed on the exterior of the administration wing. Roofing is close to completion as well, but it is temperature dependent and cannot be done in extreme cold.

In the main operations building, work is being done on lighting, fire protection, and concrete. Concrete work is expected to be completed by mid-February.

Recent photos of this work have been added to our Media page.

Move-in for City staff is anticipated for the end of June!